Aurora Avenue reconstruction from the Railroad tracks to 109th Street

Description


This project is the reconstruction of Aurora Avenue from 109th Street to the Railroad Crossing.  The existing pavement will be replaced with an urban cross-section, including curb and gutter and storm sewer.


Project Status Update 09/18/2017

Phase I of this project has started and Aurora Avenue is closed east of 109th Street/112th Street.  See Status Map below for details.

Phase I storm sewer has been installed, and street paving has begun.  The completion of Phase I paving and final grading is scheduled for the week of September 18, weather permitting.

It is currently anticipated that Phase I will reopen and Phase II work will start by the end of September.